Project Scope:
Pre-feasibility assessment of a 1000 MW HVDC interconnection, evaluating technical, economic, regulatory, and market aspects to support potential investment decisions and enhance regional renewable energy integration.
Key Responsibilities & Achievements:
Conducted techno-economic assessments, including regulatory framework gap analysis and stakeholder management strategy.
Developed project financing strategies, evaluating Public-Private Partnership (PPP) and Project Financing options; recommended Cap & Floor Hybrid Model for revenue stabilization.
Designed business and remuneration models, including Single Buyer Market trading mechanisms, SPV structure, revenue streams, operating agreements, and potential consortium investors.
Recommended HVDC ±320kV symmetric monopole topology with XLPE cables, including analysis of supply chain constraints and Tier 1 supplier availability.
Developed contracting and procurement strategies, emphasizing early supplier engagement, framework agreements, and EPCM contractor selection.
Produced global project timeline, budget analysis, and market trend assessments for converter stations and subsea cables.
Outcome:
Provided a comprehensive, risk-informed framework for further feasibility studies, supporting technical, economic, and regulatory refinements to enable the interconnector’s successful execution, strengthen regional renewable energy leadership, and advance Southeast Asia’s decarbonization objectives.